The future use of the 45-year-old Alice Hall Community Center was discussed during the Sept. 28 meeting of the Zephyrhills’ Community Redevelopment Agency (CRA).
The future use of the 45-year-old Alice Hall Community Center was discussed during the Sept. 28 meeting of Zephyrhills’ Community Redevelopment Agency (CRA).
Aaron Banks, president of Furr, Wegman & Banks Architects, P.A., said the building is “beyond its useful life.” After inspecting the structure, Banks said upgrading it to current codes would be costly and would amount to a compromise.
He cited stair-step cracking affecting the foundation, aged doors and windows, insulation problems, and accessibility issues. He also noted that restrooms are no longer used as intended and have been converted to storage.
Banks said major improvements would likely include replacing mechanical systems—such as air conditioning, which is about 22 years old—and updating an outdated, power-inefficient lighting system. He added that the building’s condition limits its usability and discourages people from using it.
CRA board member Charles Proctor said the building likely needs to be torn down and suggested a new community center should resemble Zephyrhills City Hall and the Library, both brick structures.
Mayor Melonie Bahr Monson said the city needs to address Alice Hall soon because of planned work at Zephyr Park, where changes are still being planned, including elevating areas for playgrounds, restrooms, and a Splash Pad; adding a boardwalk across Zephyr Lake; and installing new sidewalks.
In other business, the CRA approved its FY 2026–2027 budget of $4,893,381, an increase of $990,159 from FY 2025–2026.